Onshore - LNG Solutions
Quintero LNG
Two 160,000m³

full containment tanks

10,000m³

tank

400 MMSCFD

sendout

1.7km

Jetty

Scope
EPC
Location
Chile
Highlights
  • Developed the LNG import and regasification terminal from concept through to EPC 
  • Fast track project to deliver first gas 
    • Concept to EPC award in 11 months 
    • EPC to first gas in 27 months  
  • Designed for one of the most seismically active regions in the world 
    • Designed to survive a Tsunami

The Chilean LNG Project created a new grass-roots LNG receiving terminal located at Quintero Bay, approximately 160 km northwest of Santiago, Chile. The project scope included complete ship unloading facilities, LNG storage, regasification, and sendout facilities. The project also included provision for an early gas option to allow fast-tracking the marine facilities and LNG unloading, to enable gas to be unloaded and regasified to sendout before completion of the full containment LNG storage tanks.