Energy Transition - Low Carbon Fuels

3 X 4.4 MTPA
LNG export facility
165,000 m3
full containment LNG storage tank
80% to 405%
speed range
APCI
C3MR Technology
Scope
Pre-Feed, FERC FEED & EPFC
Location
Freeport, TX
Highlights
- Design for 0.9 Mtpa carbon capture
- Three trains successfully started
- Full CO2 capture from feed gas
- Solvent Selection Study
- BASF OASE purple–activated amine
- Thermal integration within the facility
McDermott and its JV partners, Chiyoda and Zachry Group, achieved substantial completion of Trains 1, 2 and 3, bringing the project to full commercial operation. The project scope included three pre-treatment trains, a liquefaction facility with three trains, a second loading berth and a 165,000 m3 full containment LNG storage tank. The Freeport LNG facility incorporates the largest electric motor-driven refrigeration compressors in the world and will significantly improve North America's energy export capabilities.